Operations and Technology Management Case Study: Critical Path Method

Facts:
The information in the table pertains to a project that is about to commence. As a project manager, which activities would you be concerned with in terms of timely project completion? Explain.
ActivityPrecedesEstimated Time (Days)
ab15
bc,d12
ce6
dend5
eend3
fg,h8
gI8
hJ9
iEnd7
jK14
kEnd6
 
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list included estimated completion times for activities and precedence relationship.
ActivityPrecedesOptimisticMost LikelyPessimisticExpected Time
Ad,f2464
De68108
Eh79129
Hend2353
Fg3485
Gend5797
Bi2232
Ij2363
Jk3454
Kend4585
Cm58128
Mn1111
No67118
Oend891310
 
Problems:
  1. Draw a precedence diagram.
  2. Find the critical path.
  3. Determine the length of the project.
 
Solutions:
A.
1. Draw a precedence diagram:
critical path 1
2. Find the critical path -  Critical Path: fhjk
3. Determine the length of the project - Projected Length of the Project: 37 days
 
B.
1. Draw a precedence diagram:
critical path 2
2. Find the critical path - Critical Path: cmno
3. Determine the length of the project - Length of the Project: 27 days